Approximate Prices for Site Work Required to Locate a Modular Home On
Private Property
| Survey |
$500-$1000 |
| Site Staking |
$100-$500 |
| Clearing/Brush Hogging ($35-$75/hr) |
$250-$5,000 |
| Tearing Down Existing Structures |
$3,500-$7,500 |
| Excavation, Backfilling and Rough Grading ($75-$125/hr) |
$1,000-$2,000 |
| Dozer Time to Pull House on Site |
$350-$1,000 |
24” Spread Footings and 12” Block for Crawlspace Including
Drain Tile, Stanchion Pads and Lead Walls
($30-$50 per lineal foot) |
$5,000-$11,000 |
24” Spread Footings and 12” Block for Basement Including
Drain Tile, Stanchion Pads and Lead Walls
($60-$75 per lineal foot) |
$10,000-$16,000 |
| Basement windows including egress window |
$1,000-$2,000 |
Beams Including Welding or Tie Downs
(Conventional Manufactured Only) (approximately $300 ea.) |
$1,500-$2,500 |
| Sill Plate and Sill Seal (Approx. $3.50 per lineal foot) |
$300-$700 |
Pea Stone Around Drain Tile and 4” Below Basement Floor
(50-100 Tons @ $20-$25 per Ton) |
$1,000-$2,500 |
| Sand for Backfill ( 50-250 Tons @ $6.00-$8.00 per Ton) |
$300-$2,000 |
| Fill Dirt @ $3.00-$5.00 per yard or Dig Pond |
$0-$5,000 |
| Basement Floor @ $2.00-$3.00 Per Square Foot |
$2,400-$7,200 |
Stanchion Posts Screwed to Floor and Joists
(must be field measured)
(Telepost @$20 ea., FHA Grade @$40 ea.) |
$100-$500 |
| Tie in to Municipal Sewer and Water (Leads) |
$1,000-$2,000 |
| Water Well |
$3,500-$6,500 |
| Septic System |
$4,500-$15,000 |
Driveway (Gravel) and Culvert
(Approx. $15 per lineal foot for 10’ Drive Plus Culvert) |
$1,500-$2,500 |
Electric Service From Pole to House (Edison)
(100 ft. overhead is free of charge, $10-15/ft. underground) |
$350-$750 |
Gas Service or Propane Installation
($350 minimum for Gas Service which is For First 100 ft.) |
$350-$1,000 |
| Electric Hook Up From Meter to Panel |
$750-$2,000 |
| Electric for Air Conditioning, Sump Pump, Basement/Crawl Lights
& Plugs |
$250-$1,500 |
| Plumbing Hookups to Water and Sewer Drops |
$1,000-$2,000 |
| Sump Pump, Sump Basket and Pipe For Sump Discharge |
$250-$750 |
| Heating (Gas Connections) and Air Conditioning (Manufactured) (Heating
$200-600, Air $1,500-$2,500) |
$1,700-$3,100 |
| Furnace, Hot Water Heater and Duct Work (BOCA Modular) |
$5,000-$7,000 |
Permits Including Perk Test or Tap Fees for Sewer and Water
(Building Permit-$250-$750, Perk Test-$130-$250, Tap Fees-$500-$5,000)
|
$400-$5,700 |
| Finish Grading, Top Soil, Landscaping |
$500-$5,000 |
Concrete for Walkways and Driveway
($2.00-$3.00 per square foot) |
$150-$2,500 |
| Gutters and Downspouts (approx. $2.00-$3.00 per lineal foot) |
$700-$2,000 |
| Steps, Porches and Decks |
$450-$2,500 |
Garage, Shed or Other Outbuildings
(1 Car-$5,000-$7,000, 2 Car-$10,000-$15,000,
10’ X 10’ Shed-$1,000-$2,500, 30’ X 40’ Pole
Building-$25,000) |
$1,000-$25,000 |
| Trash Removal |
$100-$500 |
| Crane ($2,500-$7,500) and Dozer or Tow Truck to Remove Carriers
(Mod) |
$2,500-$7,600 |
|